Project Number: 0515-01
From milepost 0 to milepost 0.68
RATA Funds: $1,035,000
Legislative District: 24
Status: Construction
Date Approved: 2015
Dry Creek Road connects US101 to Lower Elwha Road via Edgewood Drive. Alignment is relatively straight but very narrow with steep ditches. Speed limit is 25 MPH with an 85th percentile speed of 34 MPH. Current use has changed and the road operates primarily as a through route with heavier use to access Edgewood Drive to the Lower Elwha Road and the Lower Elwha Klallam Tribal reservation. This project will provide for safety improvements such as slope flattening, some widening, new surfacing, and other enhancements under the 3R guidelines